roadmap
Tony Linde
ael at star.le.ac.uk
Tue Mar 2 07:49:50 PST 2004
> This is a nice outline. Is RI the document currently being
> circulated via Kevin or how does this fit in?
Unfortunately yes - we need to get that out to the wider list as soon as the
smaller group working on it can do so.
> One other question...is there still a plan to have a videocon
> for the schema review in March?
Pass. I don't think anything has happened on organising this. And I'd like
to see further discussion on the list to at least air all the issues before
trying to discuss them in a telecon/videocon.
Cheers,
Tony.
> -----Original Message-----
> From: owner-registry at eso.org [mailto:owner-registry at eso.org]
> On Behalf Of Gretchen Greene
> Sent: 02 March 2004 14:25
> To: registry at ivoa.net
> Subject: RE: roadmap
>
> Tony, Ray et. al.,
>
> This is a nice outline. Is RI the document currently being
> circulated via Kevin or how does this fit in?
>
> One other question...is there still a plan to have a videocon
> for the schema review in March?
>
> -Gretchen
>
>
> -----Original Message-----
> From: owner-registry at eso.org [mailto:owner-registry at eso.org]
> On Behalf Of Tony Linde
> Sent: Tuesday, March 02, 2004 7:33 AM
> To: registry at ivoa.net
> Subject: roadmap
>
>
> We need to develop a roadmap of what we intend to do. I see
> the two key goals for us to achieve as being:
>
> A. Create RM v1.1 (incorporating registry schema)
>
> B. Create Registry Interface (RI) spec v1.0 (incorporating
> harvesting and query interface)
>
> I tried a schedule which had these complete by 31-Mar-05 but
> working backwards from this date made the intervening
> activities too tight (especially considering how long it has
> taken us to get where we are now and given that we should
> allow 4-6 months for testing new versions of standards). So I
> then simply worked forward from now, allowing us time for two
> more trial developments of the registry schema and one of the
> combined RM v1.1 and RI v1.0. This pushed the delivery of the
> above out to end of 2005.
>
>
> I would therefore propose the following activities as our roadmap:
>
> 2004
> ====
> 1. Publish RM V1.0 to REC status
> 31-Mar-2004
>
> 2. Agree modified Resource Metadata Schema (RMS) draft v0.91
> 30-May-2004
>
> 3. Agree modified Registry Harvesting draft (RH) v0.2
> 30-May-2004
>
> 4. Demonstrate viability of RMS v0.91 and RH v0.2 between projects
> 1-Jun-2004 to 30-Sep-2004
>
> 5. Create draft Registry Interface spec (RI) v0.1 (incl harvesting &
> query)
> 30-Nov-2004
>
> 6. Agree draft RMS v0.92
> 30-Nov-2004
>
> 2005
> ====
> 7. Demonstrate viability of RMS v0.92 and RI v0.1
> 1-Dec-2004 to 31-Mar-2005
>
> 8. Develop draft RM v1.1 (incorporating schema)
> 31-May-2005
>
> 9. Agree modified RI v0.2
> 31-May-2005
>
> 10. Demonstrate RM v1.1 and RI v0.2
> 1-Jun-2005 to 30-Sep-2005
>
> 11. Publish RM v1.1 to PR/REC
> 31-Dec-2005
>
> 12. Publish RI v1.0 to PR/REC
> 31-Dec-2005
>
> I know that this seems like a long time but the fact is that
> standards which are widely agreed and which have been proved
> to work do take many years to develop.
>
> The key to keeping this effort moving forwards is that we
> continue to develop working versions of the registry schema
> and the harvesting interface. This will allow us to prove
> that these standards work and to find the problem areas.
>
> Feel free to publish an alternative timetable if you think we
> can deliver the standards in less time than I've indicated.
> And I look forward to other comments as well.
>
> Cheers,
> Tony.
>
> __
> Tony Linde
> Phone: +44 (0)116 223 1292 Mobile: +44 (0)7753 603356
> Fax: +44 (0)116 252 3311 Email: ael at star.le.ac.uk
> Post: Department of Physics & Astronomy,
> University of Leicester
> Leicester, UK LE1 7RH
>
> Project Manager, Director,
> AstroGrid Leicester e-Science Centre
> http://www.astrogrid.org http://www.e-science.le.ac.uk/
>
>