On Tue, 7 Oct 2014, Paul Harrison wrote:

> 
> On 2014-10 -07, at 14:45, Mark Taylor <M.B.Taylor at bristol.ac.uk> wrote:
> 
> > Paul & grid,
> > 
> > On Tue, 30 Sep 2014, Paul Harrison wrote:
> > 
> >> I have uploaded a new version of the UWS 1.1 WD to http://www.ivoa.net/documents/UWS/20140930/ which contains changes which are largely as a result of the discussion that happened in this thread http://mail.ivoa.net/pipermail/grid/2014-June/002609.html
> >> 
> >> In summary the main change from the previous version is that the blocking behaviour introduced in that version has been moved from a specific custom endpoint to being signalled my a ?WAIT query parameter on the /{jobs}/{job-id} endpoint.
> > 
> > I still think there is potential for a race condition here.
> > 
> > Consider this sequence of events:
> > 
> >   1. Client requests status from server
> >   2. Server returns status: it's QUEUED
> >   3. Server changes status to EXECUTING
> >   4. Client makes blocking call to server to find out when status changes
> >   5.   ... wait ...
> >   6. Server changes status to COMPLETED
> >   7. Blocking call returns, client finds out that status is COMPLETED
> > 
> > As far as the client is concerned, the job transitions from QUEUED
> > straight to COMPLETED, it never sees the (potentially long-lived)
> > EXECUTING phase.  With the existing REST API there's nothing the
> > client can do to reliably avoid this (well, it could asychronously
> > issue another non-blocking status request after the blocking one
> > has started to check it hasn't changed, but that's (a) messy and
> > (b) not bulletproof since you don't know when the blocking call
> > actually starts blocking, i.e. how long to wait after the start
> > of the blocking call before you do it).
> > 
> > Now this won't happen very often, it's only in the unlucky case that the
> > server changes phase just after the client makes the status request.
> > Also, the consequences are not disastrous, since the terminal phases
> > (here COMPLETED) doesn't block.  Maybe for those reasons we don't
> > care enough to do anything about it.  But, it's not Right.
> 
> OK - I agree with you that it is not Right if you want to monitor PHASEs before COMPLETED, and I had not really considered this use case - though the WAIT idea does mitigate this to some extent in that  presumably if the client is interested in informing the user about intermediate stages on a regular basis, then it would probably issue a WAIT=10 (or some other small number) which is guaranteed to return after the 10 seconds, whether there has been a PHASE change or not. However, this still does not guarantee the earliest possible notice of a change of PHASE in the situation you describe.

no, in my usage I wouldn't put a short timeout on this blocking call,
what I want to do is just

   do {
      acquire phase (blocking)
      display phase
   } while ! isTerminal(phase)

so I don't need regular returns from the blocking calls.
  
> > To avoid the problem you need an an atomic operation that both
> > determines current phase and requests blocking until phase changes.
> > (An analogous issue is why in Java you are only allowed to call
> > Object.wait() if you have synchronized on that object).
> > 
> > One possibility would be for the Job document to include a blocking
> > URL that anybody is allowed to call to find out when the status
> > changes from the status reported in that document (if it's not
> > obvious how that could be implemented, I can provide a sketch).
> > Another is what I suggested when I first emailed about this issue
> > in relation to the previous WD here:
> > http://mail.ivoa.net/pipermail/grid/2014-June/002609.html
> 
> I think that I prefer your previous suggestion as a solution to this - it seems to be pretty simple for both the client and the server - though it seems to me that it would be better to have the naming of the parameter logic reversed compared with your example as that seems clearer to me.
> 
> /{jobs}/{jobid}?WAIT=20&PHASE=QUEUED
> 
> will only block if the PHASE is QUEUED (or whatever is specified) otherwise will return immediately. 
> 
> Does this do what you need?

yes.

--